Mare Island Causeway Bridge Update

Great progress continues on the Mare Island Causeway Bridge project! Here’s where things stand:

  • Bridge tower painting: 100% complete
  • Fender system painting: 100% complete
  • Mare Island logo painting: 100% complete
  • Handrail painting: 50% complete
  • Guardrail post installation: 60% complete
  • Broken pile replacement and bent cap extension: complete
  • Work under and on top of the bridge deck: ongoing
  • New sidewalk installation: ongoing
  • Light pole and lighting installation: 50% complete

Overall, the project is about 60% complete.

Due to weather and material availability delays, the anticipated completion date is now mid‑February 2027.

We’ll continue to share updates as the project moves forward!