Mare Island Causeway Bridge Update
Great progress continues on the Mare Island Causeway Bridge project! Here’s where things stand:
- Bridge tower painting: 100% complete
- Fender system painting: 100% complete
- Mare Island logo painting: 100% complete
- Handrail painting: 50% complete
- Guardrail post installation: 60% complete
- Broken pile replacement and bent cap extension: complete
- Work under and on top of the bridge deck: ongoing
- New sidewalk installation: ongoing
- Light pole and lighting installation: 50% complete
Overall, the project is about 60% complete.
Due to weather and material availability delays, the anticipated completion date is now mid‑February 2027.
We’ll continue to share updates as the project moves forward!
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Share Mare Island Causeway Bridge Update on Facebook
Share Mare Island Causeway Bridge Update on Twitter
Share Mare Island Causeway Bridge Update on Linkedin
Email Mare Island Causeway Bridge Update link













Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends